Elgin progress update - August 2012

Aberdeen, 3 August 2012 - Since the gas leak on the Elgin G4 well was stopped by a successful well intervention operation on 15 May, the G4 well has remained stable and significant further progress has been made moving towards a permanent solution.

Total and its contractors have now restarted the essential safety and support systems on board the Elgin complex and the adjacent Rowan Viking drilling rig. The key stage of putting cement plugs in place to permanently secure the well is ongoing and expected to be completed by mid-September.

Specific important milestones achieved since the leak was stopped, include:
- reinstatement of power and safety systems on the Elgin complex and Rowan Viking
- full re-manning of the Elgin PUQ accommodation (138 personnel)
- recovery of all essential functions on the Rowan Viking; some 60 people are now living on board and the rig is performing ongoing intervention operations on G4
- interim storage facilities have been provided for the discharge of oil based drilling muds during the circulation operations, pending full re-commissioning of the rig facilities
- release of the West Phoenix drilling rig, the main support vessel during the well intervention, now back drilling the Tomintoul exploration well, West of Shetland
- suspension of the drilling of a relief well by the Sedco 714 after reaching a depth of 3700 metres
- follow-up visits to Elgin by the Health and Safety Executive (HSE) and the Department of Energy & Climate Change (DECC)

The overall environmental impact of the incident will have been minimal as the majority of the condensate released evaporated, while the rest falling to sea and adding to the surface sheen also evaporated or dispersed completely within days.
Accurate estimates of the products released have been officially reported to the HSE and DECC. Total continues to work closely with DECC, Marine Scotland and other appropriate bodies to asses and monitor any environmental impacts, and will continue to do so even after the cement plugs are in place.

Total continues also to co-operate fully with the ongoing HSE investigation into the cause of the G4 leak.

11 Mar 13 08:30 United Kingdom: Total resumes production from the Elgin/Franklin area in the UK North Sea  
03 Aug 12 15:00 Elgin progress update - August 2012  
21 May 12 08:30 Elgin - Total confirms the success of the G4 well intervention  
16 May 12 11:15 Elgin leak stopped after well intervention  
15 May 12 10:30 Start of the well intervention operation to stop the Elgin leak  
10 May 12 18:10 Elgin gas leak : Weekly Update (May 4 - 10)  
04 May 12 17:40 Elgin gas leak: Weekly Summary (April 27 – May 4)  
26 Apr 12 16:05 Elgin gas leak: weekly summary (April 20-26)  
20 Apr 12 15:40 Elgin Weekly Progress Update (April 13 – 20)  
13 Apr 12 20:40 Elgin gas leak : Weekly Progress Update (6-13 April 2012)  
06 Apr 12 15:15 Elgin Platform visit confirms well intervention plans can proceed  
05 Apr 12 18:45 Next Steps To Stop The Leak Underway: Elgin Platform Safely Reboarded  
05 Apr 12 10:35 Elgin incident update  
02 Apr 12 18:30 Conference call update on Elgin incident  
02 Apr 12 13:00 Elgin gas leak: Total prepares operations to stop the leak  
31 Mar 12 12:20 Extinguishing of the flare on the Elgin platform  
30 Mar 12 18:30 Status on UK – Gas leak incident at Elgin platform in the North Sea  
30 Mar 12 13:30 Elgin incident update following press conference  
29 Mar 12 19:00 Status on UK – Gas leak incident at Elgin platform in the North Sea  
28 Mar 12 18:25 Elgin update 4 - Total E&P UK Ltd  
28 Mar 12 16:00 Elgin update 3 - Total E&P UK Ltd  
27 Mar 12 16:55 Status on UK – Gas leak incident at Elgin platform in the North Sea  
26 Mar 12 21:00 Elgin update 2 - Total E&P UK Ltd  
26 Mar 12 14:25 Elgin update 1 - Total E&P UK Ltd  
26 Mar 12 04:00 News Release 5 - Total E&P UK Ltd  
25 Mar 12 23:00 Press statement 4 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 18:45 Press Statement 3 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 16:45 Press Statement 2 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 14:00 Press Statement 1 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 13:45 Holding Statement 25 March 2012 - Total E&P UK Ltd  
By continuing browsing this website, you accept the use of cookies or other tracers for statistics of visits to optimize the functionality of the site. For more information and for tracers settings