April 20, 2012 - The two technical solutions to stop the gas leak on well G4 of the Elgin platform are progressing according to plan. As announced, drilling of the G4 relief well (G4-K1) commenced while in parallel experts continued with key tasks in preparation for the well control operation to stop the leak on the Elgin platform.

The Sedco 714 drilling rig spudded the relief well on April 18 to be used as a back-up option to the G4 well control operation. The Sedco 714 well site is located approximately 2 kilometres east of the Elgin complex in water depths of around 90 meters. The drilling began following the granting of all necessary approvals by the UK authorities.

Another drilling rig, the Rowan Gorilla V, is suspending operations on the nearby West Franklin field and will be available to be deployed by early-May.

In parallel, plans are being finalized for the positioning of the pumping vessel required for the well intervention alongside the Elgin complex. The West Phoenix is currently on standby just outside the two nautical mile Elgin exclusion zone. Total has also mobilised the intervention vessel Skandi Aker, currently in the Scottish port of Peterhead, which will also be used to support the well intervention operation.

Two helicopter trips were made this week to the Elgin platform during which Total and Wild Well Control teams were able to confirm that the Elgin PUQ provides a safe base from which to support the G4 well control operations. They also continued with work to lay out equipment and ensure that the platform systems required to support the intervention are functional.

The latest scientific flights, modelling and platform visits this week confirm a decrease in the gas leak rate, to around one third of the initial estimate of 2 kg/s of gas* made in the first days of the Elgin gas leak.

Separately, Scottish authorities said chemical testing of water and sediment samples gathered two miles from the Elgin platform indicate there has been no direct marine contamination from the G4 leak.

* approximately 200,000 m3/day

FAQ

 

Contacts

Isabelle DESMET - +33 (0)1 47 44 37 76
Charles-Etienne LEBATARD - +33 (0)1 47 44 45 91
Victoria CHANIAL - +33 (0)1 47 44 35 86
Aude COLAS DES FRANCS - +33 (0)1 47 44 47 05
Michaël CROCHET-VOUREY - +33 (0)1 47 44 81 33
Sandra DANTE - +33 (0)1 47 44 46 07
Christine de CHAMPEAUX - +33 (0)1 47 44 47 49
Hortense OURY - +33 (0)1 47 44 23 34
Florent SEGURA - +33 (0)1 47 44 31 38
Frédéric TEXIER - +33 (0)1 47 44 38 16
Anastasia ZHIVULINA - +33 (0)1 47 44 76 29 
 

11 Mar 13 08:30 United Kingdom: Total resumes production from the Elgin/Franklin area in the UK North Sea  
03 Aug 12 15:00 Elgin progress update - August 2012  
21 May 12 08:30 Elgin - Total confirms the success of the G4 well intervention  
16 May 12 11:15 Elgin leak stopped after well intervention  
15 May 12 10:30 Start of the well intervention operation to stop the Elgin leak  
10 May 12 18:10 Elgin gas leak : Weekly Update (May 4 - 10)  
04 May 12 17:40 Elgin gas leak: Weekly Summary (April 27 – May 4)  
26 Apr 12 16:05 Elgin gas leak: weekly summary (April 20-26)  
20 Apr 12 15:40 Elgin Weekly Progress Update (April 13 – 20)  
13 Apr 12 20:40 Elgin gas leak : Weekly Progress Update (6-13 April 2012)  
06 Apr 12 15:15 Elgin Platform visit confirms well intervention plans can proceed  
05 Apr 12 18:45 Next Steps To Stop The Leak Underway: Elgin Platform Safely Reboarded  
05 Apr 12 10:35 Elgin incident update  
02 Apr 12 18:30 Conference call update on Elgin incident  
02 Apr 12 13:00 Elgin gas leak: Total prepares operations to stop the leak  
31 Mar 12 12:20 Extinguishing of the flare on the Elgin platform  
30 Mar 12 18:30 Status on UK – Gas leak incident at Elgin platform in the North Sea  
30 Mar 12 13:30 Elgin incident update following press conference  
29 Mar 12 19:00 Status on UK – Gas leak incident at Elgin platform in the North Sea  
28 Mar 12 18:25 Elgin update 4 - Total E&P UK Ltd  
28 Mar 12 16:00 Elgin update 3 - Total E&P UK Ltd  
27 Mar 12 16:55 Status on UK – Gas leak incident at Elgin platform in the North Sea  
26 Mar 12 21:00 Elgin update 2 - Total E&P UK Ltd  
26 Mar 12 14:25 Elgin update 1 - Total E&P UK Ltd  
26 Mar 12 04:00 News Release 5 - Total E&P UK Ltd  
25 Mar 12 23:00 Press statement 4 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 18:45 Press Statement 3 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 16:45 Press Statement 2 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 14:00 Press Statement 1 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 13:45 Holding Statement 25 March 2012 - Total E&P UK Ltd  
By continuing browsing this website, you accept the use of cookies or other tracers for statistics of visits to optimize the functionality of the site. For more information and for tracers settings