Elgin Platform visit confirms well intervention plans can proceed

April, 6, 2012, 15h15 (Paris time) - The reconnaissance mission to the Elgin complex by a team of Total experts and specialist contractors has confirmed that planning for a well intervention operation to bring the leaking G4 well under control can continue as planned.


After ensuring all necessary safety requirements had been met, the team disembarked from the helicopter and found no presence of gas on the Elgin PUQ (Process, Utilities, Quarters) platform, which is connected by a 90-metre bridge to the Well Head Platform (WHP) where the leak is located. The access routes to the WHP were also found to be free of gas. The team was able to access the rig.


The structural condition of the platform, the G4 wellhead and surrounding areas, including the rig, was found to be unchanged since the complex was evacuated on March 25th, as was the overall safety situation.


The visual inspection confirmed that the leak is coming from the G4 wellhead at WHP deck level. In parallel, a ROV (Remote Operated Vehicle) survey confirmed no underwater gas leak.


The team was also able to identify piping & hose routing options plus tie-in points for well control equipment. Specialists plan to return to the platform within the coming days to complete the survey and develop detailed plans.


Speaking shortly after returning from the platform, Wild Well Control said: “We achieved our goals. Everything went as we would have hoped and the planned well intervention is achievable. There is certainly no showstopper to launch the well control operation.”


The reconnaissance team will now give Total management a detailed debriefing, enabling them to further develop plans for the well intervention.

 
At the same time, preparations are still proceeding for the drilling of a relief well and a backup relief well.


In parallel, various indications such as regular visual observations from a nearby vessel and temperature measurements seem to suggest that the gas leak rate has decreased during the last few days.

Contacts

Isabelle DESMET - +33 (0)1 47 44 37 76
Charles-Etienne LEBATARD - +33 (0)1 47 44 45 91
Victoria CHANIAL - +33 (0)1 47 44 35 86
Aude COLAS DES FRANCS - +33 (0)1 47 44 47 05
Michaël CROCHET-VOUREY - +33 (0)1 47 44 81 33
Sandra DANTE - +33 (0)1 47 44 46 07
Christine de CHAMPEAUX - +33 (0)1 47 44 47 49
Hortense OURY - +33 (0)1 47 44 23 34
Florent SEGURA - +33 (0)1 47 44 31 38
Frédéric TEXIER - +33 (0)1 47 44 38 16
Anastasia ZHIVULINA - +33 (0) 1 47 44 76 29


11 Mar 13 08:30 United Kingdom: Total resumes production from the Elgin/Franklin area in the UK North Sea  
03 Aug 12 15:00 Elgin progress update - August 2012  
21 May 12 08:30 Elgin - Total confirms the success of the G4 well intervention  
16 May 12 11:15 Elgin leak stopped after well intervention  
15 May 12 10:30 Start of the well intervention operation to stop the Elgin leak  
10 May 12 18:10 Elgin gas leak : Weekly Update (May 4 - 10)  
04 May 12 17:40 Elgin gas leak: Weekly Summary (April 27 – May 4)  
26 Apr 12 16:05 Elgin gas leak: weekly summary (April 20-26)  
20 Apr 12 15:40 Elgin Weekly Progress Update (April 13 – 20)  
13 Apr 12 20:40 Elgin gas leak : Weekly Progress Update (6-13 April 2012)  
06 Apr 12 15:15 Elgin Platform visit confirms well intervention plans can proceed  
05 Apr 12 18:45 Next Steps To Stop The Leak Underway: Elgin Platform Safely Reboarded  
05 Apr 12 10:35 Elgin incident update  
02 Apr 12 18:30 Conference call update on Elgin incident  
02 Apr 12 13:00 Elgin gas leak: Total prepares operations to stop the leak  
31 Mar 12 12:20 Extinguishing of the flare on the Elgin platform  
30 Mar 12 18:30 Status on UK – Gas leak incident at Elgin platform in the North Sea  
30 Mar 12 13:30 Elgin incident update following press conference  
29 Mar 12 19:00 Status on UK – Gas leak incident at Elgin platform in the North Sea  
28 Mar 12 18:25 Elgin update 4 - Total E&P UK Ltd  
28 Mar 12 16:00 Elgin update 3 - Total E&P UK Ltd  
27 Mar 12 16:55 Status on UK – Gas leak incident at Elgin platform in the North Sea  
26 Mar 12 21:00 Elgin update 2 - Total E&P UK Ltd  
26 Mar 12 14:25 Elgin update 1 - Total E&P UK Ltd  
26 Mar 12 04:00 News Release 5 - Total E&P UK Ltd  
25 Mar 12 23:00 Press statement 4 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 18:45 Press Statement 3 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 16:45 Press Statement 2 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 14:00 Press Statement 1 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 13:45 Holding Statement 25 March 2012 - Total E&P UK Ltd  
By continuing browsing this website, you accept the use of cookies or other tracers for statistics of visits to optimize the functionality of the site. For more information and for tracers settings