Press Statement 3 - 25 March 2012 - Total E&P UK Ltd

TOTAL E&P UK Limited confirms that an incident occurred at 12.15 hrs on the Elgin field which is located in the Central Graben Area, 240km off Aberdeen.
Work is continuing to control a gas release which occurred earlier today at the wellhead platform on the Elgin field.
All personnel have been accounted for and no injuries have been reported. All non essential personnel on the Elgin PUQ and wellhead platform, along with all personnel on the Rowan Viking drilling rig have been evacuated. Following an earlier transfer to neighbouring installations, these personnel are now being transferred back to Aberdeen until the situation is resolved.
Emergency procedures are focusing on the welfare of all personnel involved and in resolving the current situation as quickly as possible.
We will continue to make information available via the following:
www.facebook.com/TotalEPUK
www.twitter.com/TotalEPUK

Telephone number for media enquiries – 01224 296988
Telephone number for relative enquiries – 01224 296866

11 Mar 13 08:30 United Kingdom: Total resumes production from the Elgin/Franklin area in the UK North Sea  
03 Aug 12 15:00 Elgin progress update - August 2012  
21 May 12 08:30 Elgin - Total confirms the success of the G4 well intervention  
16 May 12 11:15 Elgin leak stopped after well intervention  
15 May 12 10:30 Start of the well intervention operation to stop the Elgin leak  
10 May 12 18:10 Elgin gas leak : Weekly Update (May 4 - 10)  
04 May 12 17:40 Elgin gas leak: Weekly Summary (April 27 – May 4)  
26 Apr 12 16:05 Elgin gas leak: weekly summary (April 20-26)  
20 Apr 12 15:40 Elgin Weekly Progress Update (April 13 – 20)  
13 Apr 12 20:40 Elgin gas leak : Weekly Progress Update (6-13 April 2012)  
06 Apr 12 15:15 Elgin Platform visit confirms well intervention plans can proceed  
05 Apr 12 18:45 Next Steps To Stop The Leak Underway: Elgin Platform Safely Reboarded  
05 Apr 12 10:35 Elgin incident update  
02 Apr 12 18:30 Conference call update on Elgin incident  
02 Apr 12 13:00 Elgin gas leak: Total prepares operations to stop the leak  
31 Mar 12 12:20 Extinguishing of the flare on the Elgin platform  
30 Mar 12 18:30 Status on UK – Gas leak incident at Elgin platform in the North Sea  
30 Mar 12 13:30 Elgin incident update following press conference  
29 Mar 12 19:00 Status on UK – Gas leak incident at Elgin platform in the North Sea  
28 Mar 12 18:25 Elgin update 4 - Total E&P UK Ltd  
28 Mar 12 16:00 Elgin update 3 - Total E&P UK Ltd  
27 Mar 12 16:55 Status on UK – Gas leak incident at Elgin platform in the North Sea  
26 Mar 12 21:00 Elgin update 2 - Total E&P UK Ltd  
26 Mar 12 14:25 Elgin update 1 - Total E&P UK Ltd  
26 Mar 12 04:00 News Release 5 - Total E&P UK Ltd  
25 Mar 12 23:00 Press statement 4 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 18:45 Press Statement 3 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 16:45 Press Statement 2 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 14:00 Press Statement 1 - 25 March 2012 - Total E&P UK Ltd  
25 Mar 12 13:45 Holding Statement 25 March 2012 - Total E&P UK Ltd  